A large global healthcare company needed structured cabling installation for a new twin site data centre client in Slough and Docklands.
We designed, supplied and installed a high-performance Leviton E2XHD cabling infrastructure to provide Cat 6A and OM4 connectivity for 32 racks across both sites, with over 550 Cat 6A outlets and 370 LC ports. As part of this, we carried out various overhead tray work modifications due to the constrained overhead space.
Our strong relationships with market-leading cable suppliers helped us to deliver short lead times and excellent value to the client, and the project was successfully completed on schedule.